28th July 2025


In National House Building Council v Peabody Trust [2025] EWCA Civ 932, the Court of Appeal (Coulson, Lewison and Moylan LLJ) upheld the High Court’s decision to dismiss an application made by the NHBC for summary judgment / strike out of a claim brought by the Peabody Trust.

The insurance cover under scrutiny was the widely used ‘Option 1 – Insolvency cover before practical completion’ extension to the NHBC Buildmark policy which applies if you [i.e. the employer / insured] “…have to pay more to complete the building of the home(s), because the contractor is insolvent or commits fraud”.

The Court of Appeal’s decision confirms that the NHBC’s interpretation, that the cause of action arose at, and time for limitation purposes began to run from the moment of the contractor’s insolvency, is wrong in law. Instead, the cause of action accrues when the employer (insured) has to pay more to complete the building of the home(s).

Mek Mesfin acted acted with Noel Casey KC of 7KBW for the successful Respondent, the Peabody Trust, instructed by Mark London, Will O’Brien and Alicia Ogborn of Devonshires.

The full judgment is available here.

Register for updates

Subscribe to our regular newsletters, bulletins and case updates relating to our core areas of expertise.

Register

Would you like to
 know more?

For help and advice talk to a member of our clerking team. They can advise on the best options for your matter.

Call: +44 (0) 20 7842 5555

  • This field is for validation purposes and should be left unchanged.

Search

Shortlist close
Title Type CV Email

Remove All

Download