26th July 2023
The TCC yesterday handed down judgment in Home Group Limited v MPS Housing Limited [2023] EWHC 1926 (KB), enforcing an adjudication for over £6.5 million. Matthew Thorne (instructed by Devonshires Solicitors LLP) acted for the successful claimant.
Background
The claimant (Home Group) is a social housing provider and owns thousands of properties in England and Scotland. The underlying contract, on a JCT Measured Term 2011 form, required the defendant (MPS) to carry out planned and reactive maintenance, minor and emergency works to Home Group’s properties in the south-east of England. The Orders carried out under the contract were generally low value, high volume.
It was decided in an earlier adjudication that MPS had committed a repudiatory breach of the contract in May 2022, bringing the contract to an end. Home Group then commenced a further adjudication for quantification of its losses. The Referral contained a substantial expert report, witness evidence and large quantities of documents and data, covering many thousands of small value work orders, to which MPS was required to respond. In April 2023, the Adjudicator decided that MPS was liable to Home Group for sums in excess of £6.5 million.
MPS refused to pay and sought to resist enforcement. It contended that it had been unable properly to digest and respond to the material served with the Referral in the time available, and that this was a breach of natural justice, such that the Decision was unenforceable.
The Decision
The Court disagreed. Mr Justice Constable reviewed the authorities on complexity and time-pressure, and distilled the legal position in paragraph 50 as follows:
The Judge went on to conclude that, on the facts, MPS’s position was “without merit”. It ought to have taken up an offer to inspect the underlying data on the basis of sampling when that proposal was made some months earlier; and it had received a draft copy of Home Group’s expert report a number of weeks before the Adjudication commenced. Spot checks and sampling are a permissible procedure for an adjudicator to adopt. In the time available, MPS had ultimately been able to identify significant areas of dispute and advance arguments based on sampling. Whilst MPS’s adjudication response “was less comprehensive than would be expected in litigation or arbitration… that is plainly not the test”.
The Judge also gave welcome clarity on the test of materiality, confirming that a party challenging enforcement must show that the alleged breach of natural justice must have led to a material difference in the outcome. The Judge noted at [59] that, despite the time which had passed since the adjudication, MPS had not presented “evidence which they say they would have been able to produce given more time,” and failed to acknowledge the scrutiny given by the Adjudicator to the competing factual evidence.
To take away…
This decision is an important reminder to paying parties that, when faced with claims, they will be expected to engage proactively. Where an adjudicator has decided that he or she is able to do “broad justice between the parties,” arguments of insufficient information, complexity or a lack of time are unlikely to be met with sympathy from the TCC upon enforcement. Where evidence is voluminous, an adjudicator can permissibly proceed by sampling or spot checks.
A strong case will be required if such a challenge is to succeed, and a responding party will need to show that any breach actually affected the outcome.
The full judgment can be found here
For help and advice talk to a member of our clerking team. They can advise on the best options for your matter.
Call: +44 (0) 20 7842 5555